Tracking major resources for automated progress monitoring of construction activities: masonry work case | Kütüphane.osmanlica.com

Tracking major resources for automated progress monitoring of construction activities: masonry work case

İsim Tracking major resources for automated progress monitoring of construction activities: masonry work case
Yazar Işın, Gürşans Güven, Ergen, E.
Basım Tarihi: 2021-10-21
Basım Yeri - Emerald
Konu Data fusion, Field test, Progress monitoring, Resource tracking, RFID, Sensor-based technologies
Tür Süreli Yayın
Dil İngilizce
Dijital Evet
Yazma Hayır
Kütüphane: Özyeğin Üniversitesi
Demirbaş Numarası 1471-4175
Kayıt Numarası 6659cf6a-c55f-4222-85af-5d2202179a7d
Lokasyon Civil Engineering
Tarih 2021-10-21
Notlar TÜBİTAK
Örnek Metin Purpose: The purpose of this study is to monitor the progress of construction activities in an automated way by using sensor-based technologies for tracking multiple resources that are used in building construction. Design/methodology/approach: An automated on-site progress monitoring approach was proposed and a proof-of-concept prototype was developed, followed by a field experimentation study at a high-rise building construction site. The developed approach was used to integrate sensor data collected from multiple resources used in different steps of an activity. It incorporated the domain-specific heuristics that were related to the site layout conditions and method of activity. Findings: The prototype estimated the overall progress with 95% accuracy. More accurate and up-to-date progress measurement was achieved compared to the manual approach, and the need for visual inspections and manual data collection from the field was eliminated. Overall, the field experiments demonstrated that low-cost implementation is possible, if readily available or embedded sensors on equipment are used. Originality/value: Previous studies either monitored one particular piece of equipment or the developed approaches were only applicable to limited activity types. This study demonstrated that it is technically feasible to determine progress at the site by fusing sensor data that are collected from multiple resources during the construction of building superstructure. The rule-based reasoning algorithms, which were developed based on a typical work practice of cranes and hoists, can be adapted to other activities that involve transferring bulk materials and use cranes and/or hoists for material handling.
DOI 10.1108/CI-05-2020-0081
Cilt 21
Kaynağa git Özyeğin Üniversitesi Özyeğin Üniversitesi
Özyeğin Üniversitesi Özyeğin Üniversitesi
Kaynağa git

Tracking major resources for automated progress monitoring of construction activities: masonry work case

Yazar Işın, Gürşans Güven, Ergen, E.
Basım Tarihi 2021-10-21
Basım Yeri - Emerald
Konu Data fusion, Field test, Progress monitoring, Resource tracking, RFID, Sensor-based technologies
Tür Süreli Yayın
Dil İngilizce
Dijital Evet
Yazma Hayır
Kütüphane Özyeğin Üniversitesi
Demirbaş Numarası 1471-4175
Kayıt Numarası 6659cf6a-c55f-4222-85af-5d2202179a7d
Lokasyon Civil Engineering
Tarih 2021-10-21
Notlar TÜBİTAK
Örnek Metin Purpose: The purpose of this study is to monitor the progress of construction activities in an automated way by using sensor-based technologies for tracking multiple resources that are used in building construction. Design/methodology/approach: An automated on-site progress monitoring approach was proposed and a proof-of-concept prototype was developed, followed by a field experimentation study at a high-rise building construction site. The developed approach was used to integrate sensor data collected from multiple resources used in different steps of an activity. It incorporated the domain-specific heuristics that were related to the site layout conditions and method of activity. Findings: The prototype estimated the overall progress with 95% accuracy. More accurate and up-to-date progress measurement was achieved compared to the manual approach, and the need for visual inspections and manual data collection from the field was eliminated. Overall, the field experiments demonstrated that low-cost implementation is possible, if readily available or embedded sensors on equipment are used. Originality/value: Previous studies either monitored one particular piece of equipment or the developed approaches were only applicable to limited activity types. This study demonstrated that it is technically feasible to determine progress at the site by fusing sensor data that are collected from multiple resources during the construction of building superstructure. The rule-based reasoning algorithms, which were developed based on a typical work practice of cranes and hoists, can be adapted to other activities that involve transferring bulk materials and use cranes and/or hoists for material handling.
DOI 10.1108/CI-05-2020-0081
Cilt 21
Özyeğin Üniversitesi
Özyeğin Üniversitesi yönlendiriliyorsunuz...

Lütfen bekleyiniz.